    The Granny Flat Approval Process in South Africa (Step by Step)

    Most homeowners think building a granny flat is a building plan problem. It is actually a town planning problem first. Here is the full sequence of steps and the documents required at each.

    8 min readUpdated 2026-10-12Registered town planner
    The Granny Flat Approval Process in South Africa (Step by Step)
    01

    Step 1 - Pull a current zoning certificate

    Confirm zoning, primary rights, consent uses and title conditions before spending any design money.

    02

    Step 2 - Commission a site plan and sketch design

    A draughtsperson or architect prepares an existing-and-proposed site plan showing the proposed granny flat footprint, distances to boundaries, parking, services and existing structures.

    03

    Step 3 - Engage a town planner

    The planner prepares the motivational report, completes the application form, manages neighbour consultation, lodges with the municipality, attends the tribunal if needed and tracks the decision.

    05

    Step 5 - Public notice

    Adjoining owners are formally notified, the application is advertised in the press where required, and the 30-day comment period runs.

    06

    Step 6 - Municipal Planning Tribunal decision

    The MPT decides on the consent. Conditions of approval typically include FAR, parking, services and design controls.

    07

    Step 7 - Building plans

    Architectural plans are prepared by a registered draughtsperson, submitted to building control, and approved before construction can start.

    08

    Step 8 - Construction and occupation certificate

    After construction, the municipality issues a certificate of occupation once compliance is confirmed.

    Municipality-specific notes

    • Cape Town

      City of Cape Town uses the Municipal Planning By-Law (MPBL, 2015) and the Development Management Scheme (DMS). Applications run through the eDevelopment Application Management System (eDAMS).

    • Johannesburg

      City of Johannesburg operates under the Municipal Planning By-Law (2016) and the Joburg Town Planning Scheme. Applications lodge via the JoziPlan online portal.

    • Tshwane (Pretoria)

      City of Tshwane uses the Tshwane Town-planning Scheme (2008) under the Land Use Management By-Law. The Spatial Planning division handles intake.

    • eThekwini (Durban)

      eThekwini uses the eThekwini Town Planning Scheme administered under the KwaZulu-Natal Planning and Development Act and SPLUMA.

    Frequently asked questions

    Do I need a town planner?+

    Strictly no, but in practice yes. Self-lodged consent use applications have a high refusal rate due to incomplete motivation and missing documents.

    What is the cost breakdown?+

    Council fees are set by each municipality's tariff schedule. Third-party costs to budget for: draughtsperson R8,000-R20,000 and construction R8,000-R15,000 per m². The Landlodz fee is published on the Landlodz pricing page.

    Can I appeal a refusal?+

    Yes, under SPLUMA. The Landlodz appeal flow handles this.