    The Town Planning Process in South Africa Explained

    Every South African land use application follows the same six-step process under SPLUMA. The detail differs by municipality and application type, but the spine is universal.

    8 min readUpdated 2026-10-12Registered town planner
    The Town Planning Process in South Africa Explained
    01

    Step 1 - Feasibility

    Pull the zoning certificate, title deed and any overlays. Identify the cheapest route (consent use vs rezoning vs departure). Confirm services capacity.

    02

    Step 2 - Drafting

    Motivational report, site plan, locality plan, neighbour consent or notification, application forms.

    03

    Step 3 - Lodgement

    Submit to the municipality with proof of payment. The council acknowledges and assigns an application number.

    04

    Step 4 - Public participation

    30-day comment period. Newspaper, gazette and direct neighbour notice.

    05

    Step 5 - Decision

    Municipal Planning Tribunal decides. Approval comes with conditions; refusal comes with reasons.

    06

    Step 6 - Appeal (if needed)

    Lodge with the SPLUMA appeal authority within the prescribed period (usually 21 days).

    Municipality-specific notes

    • Cape Town

      City of Cape Town uses the Municipal Planning By-Law (MPBL, 2015) and the Development Management Scheme (DMS). Applications run through the eDevelopment Application Management System (eDAMS).

    • Johannesburg

      City of Johannesburg operates under the Municipal Planning By-Law (2016) and the Joburg Town Planning Scheme. Applications lodge via the JoziPlan online portal.

    • Tshwane (Pretoria)

      City of Tshwane uses the Tshwane Town-planning Scheme (2008) under the Land Use Management By-Law. The Spatial Planning division handles intake.

    • eThekwini (Durban)

      eThekwini uses the eThekwini Town Planning Scheme administered under the KwaZulu-Natal Planning and Development Act and SPLUMA.

    Frequently asked questions

    How long does the whole process take?+

    Consent use 4-8 months. Rezoning 9-18 months. Subdivision 6-15 months. Add 6 months for appeals.